信息系統(tǒng)項目管理師考試英語練習題(十二)

1、Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress.

A. analyze    

B. track      

C. level     

D. extend

信管網解析:

開發(fā)項目進度表通常是一個迭代過程。它確定項目活動和里程碑的計劃開始和結束日期。進度計劃的制定可能需要對工期估算和資源估算進行審查和修訂,以創(chuàng)建一個批準的項目進度計劃,作為()進度的基線。

A、 分析

B、 軌道

C、 水平

D、 擴展

信管網參考答案:B

2、The ( ) is a  general description of the architecture of a workflow management system  used by  the WFMC, in which  the main components and  the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several .()  

(1)

A. waterfall model                      

B. workflow reference model            

C. evolutionary model                    

D. spiral model  

(2)

A. workflow engines                      

B. processes  

C. workflow threads                      

D. tasks  

信管網解析:

()是WFMC使用的工作流管理系統(tǒng)架構的一般描述,其中總結了主要組件和相關接口。工作流執(zhí)行服務是由多個工作流系統(tǒng)組成的工作流系統(tǒng)的核心

(一)

A、 瀑布模型

B、 工作流參考模型

C、 進化模型

D、 螺旋模型

(二)

A、 工作流引擎

B、 過程

C、 工作流線程

D、 任務

信管網參考答案:B、A


信管網訂閱號

信管網視頻號

信管網抖音號

溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!

信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。

信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。

相關內容

發(fā)表評論  查看完整評論  

推薦文章

精選

課程

提問

評論

收藏